9
- For hoisting ensure that the weight is evenly dis-
tributed and that all previous steps are carried out
correctly.
If there is not enough space it may not be possible
to remove the lifting bars. In the example below, the
lifting bars can not be removed on the right-hand side
of the 6th AHU section, as the wall is too close and
the lifting bars are too long. It would be possible
to remove them from the left-hand side, if the third
AHU section has not yet been placed. Ensure that
the bolt and the locking plate are removed from the
right-hand side of the lifting bar, when the 6th AHU
section has been positioned.
Figure 9. Location Diagram
Figure 6. Fastening the lifting bars - 2
Figure 7. Fastening the lifting bars - 3
• After inserting the lifting bar, re-insert the bolt and
locking plate in the correct position.
• Position the lifting cables on the lifting bars (4 or 6
off). Evenly positioned spacer bars should be used
between the lifting cables to prevent damage to the
top of the unit and ensure that no excess pressure is
applied to the side panels.
Figure 8. Vertical transport using spacer bars
Lifting bar
Wall
5. ASSEMBLY
5.1. AHU Assembly
• Place the anti-vibration mats where the first casing
section will be positioned.
• Place the first casing section on the anti-vibration
mats, and then remove the lifting bars.
Figure 10. Anti-vibration mats