
START-UP CHECK LIST
Equipment sold by: Contract No.:
Installed by: Contract No.:
Site address:
Start-up date:
Equipment type and serial numbers:
Electrical data:
Supply voltage: Ph. V Ph. 2 V Ph. 3 V
Nominal voltage: V % network voltage:
Current draw: Ph. 1 A Ph. 2 A Ph. 3 A
Main circuit breaker rating: A
Physical data:
Condenser: Cooler:
Entering air temperature: °C Entering water temperarture: °C
Leaving air temperature: °C Leaving water temperature: °C
Pressure drop (air): kPa Pressure drop (water): kPa
Discharge air pressure: Pa Suction pressure: kPa
Fan speed: r/s or rpm
Fan motor input: Ph. 1 V Ph. 2 V Ph. 3 V
Ph. 1 V Ph. 2 V Ph. 3 V
Safety device setting:
High pressure switch: cut-out kPa: cut-in kPa
Low-pressure switch: cut-out kPa cut-in kPa
Safety thermostat: cut-out °C cut-in °C
Control thermostat: cut-out first step °C cut-in first step °C
cut-out second step °C cut-in second step °C
Oil level:
Oil visible in sight glass?:
Colour of moisture indicator:
Air bubbles visible in sight glass?:
Accessories:
-
-
Commissioning engineer (name):
Purchase order number:
NOTE: Please fill in this sheet during the installation
Komentáře k této Příručce