Title: Chiller High Voltage Motor Terminations Lesson Plan #: NMH30L050303
TERMINAL OBJECTIVE:
1.1 Given the applicable work instructions, reference documents, tools and equipment the trainee will, inspect,
repair, install and rework the chiller motor high voltage terminal connections. Mastery will be demonstrated by
successfully installing a ceramic motor terminal assembly.
1.1.1 Discuss the process of inspecting and re-torquing the chiller motor terminals along with the
tag out expectations on the permit which will allow personnel to safely perform this task.
1.1.2 Install a high voltage chiller motor terminal assembly.
1.1.3 Discuss the repair process for the compressor motor leads.